July 2021
California Community Colleges Capital Outlay Reappropriations
(In Thousands)
| Reappropriation | All Years | |||||
| College | Project | Phase | State Cost | State Cost | Total Costa | |
| Approved by Legislative Packageb | ||||||
| San Francisco | Cloud Hall renovation | W | $678 | $20,542 | $62,699 | |
| Fullerton | Music/drama replacement complex | W | 1,637 | 41,549 | 53,053 | |
| Clovis | New applied technology building, phase 1 | C | 24,089 | 25,883 | 50,552 | |
| Sierra | Science building replacement, phase 1 | W | 1,138 | 25,609 | 50,263 | |
| West Valley | Learning resource center renovation | C | 17,815 | 19,438 | 38,669 | |
| Sierra | Gymnasium renovation and expansion | W | 1,141 | 27,865 | 36,637 | |
| Cuyamaca | Instructional building replacement, phase 1 | W | 415 | 14,513 | 28,555 | |
| Siskiyous | Theater arts building renovation | W | 1,076 | 27,482 | 27,482 | |
| Alameda | Aviation replacement complex | W | 514 | 12,718 | 25,114 | |
| San Francisco (Alemany Center) | Seismic and code renovations | W | —c | 12,184 | 19,553 | |
| Chabot | Maintenance and operations replacement building | W | 249 | 8,846 | 17,529 | |
| Sequoias | Basic skills replacement center | C | 13,876 | 15,241 | 16,913 | |
| Cosumnes River (Elk Grove Center) | Center expansion, phase 2 | C | 8,102 | 8,512 | 16,509 | |
| Barstow | Hydronic loop and water infrastructure replacement | W | 282 | 9,920 | 9,920 | |
| Canyons | Boykin Hall renovation | C | 4,332 | 4,729 | 9,218 | |
| Santa Rosa (Public Safety Training Center) | Center expansion | W | 169 | 4,975 | 7,427 | |
| Yuba | Life and physical science building renovation | W | 203 | 3,652 | 4,657 | |
| Subtotal | ($75,716) | ($283,658) | ($474,750) | |||
| Approved by Three-Way Agreementd | ||||||
| Los Angeles Trade-Technical | Design and media arts replacement building | W | $1,040 | $35,671 | $84,841 | |
| Los Angeles Valley | Academic 2 replacement building | W | 706 | 23,801 | 57,297 | |
| Mission College | New performing arts building | W | 450 | 14,007 | 54,712 | |
| Los Angeles Pierce | Industrial technololgy replacement building | W | 509 | 16,955 | 41,028 | |
| West Los Angeles | Plant facilities/shops replacement building | W | 193 | 5,751 | 14,138 | |
| Subtotal | ($2,898) | ($96,185) | ($252,016) | |||
| Totals | $78,614 | $379,843 | $726,766 | |||
| Notes: | ||||||
| a Community college districts typically issue local general obligation bonds to pay for a share of project costs. | ||||||
| b Included in Chapter 21 of 2021 (AB 128, Ting). | ||||||
| c Extension of liquidation period for funds initially provided in 2018-19 Budget Act. That budget act provided $536,000 for working drawings--some of which is still available to cover the remaining cost of working drawings. | ||||||
| d Included in Chapter 69 of 2021 (SB 129, Skinner). Each of these projects had cost increases in excess of 20 percent, as detailed on pages 9 through 17 of this Public Works Board agenda. | ||||||
| Unless otherwise noted, table shows reappropriations of 2020-21 funds in the 2021-22 Budget Act. | ||||||
| W = working drawings. C = construction. | ||||||