July 2023

Community Colleges

California Community Colleges Capital Outlay Reappropriations

Proposition 51 Bond Funds (In Thousands)

    Reappropriation          All Years
College Project Phase State Cost   State Cost Total Costa
San Francisco (Ocean Center) Utility infrastructure replacement C $58,082   $63,461 $79,326
Laney New learning resource center C 22,812   24,417 75,686
San Francisco Cloud Hall renovation P b   20,542 62,699
Santa Ana Russell Hall replacement C 2,719   20,729 49,031
Cypress Fine arts building renovation W c   18,133 29,801
Alameda Aviation Complex replacement P d   12,718 25,114
San Francisco (Alemany Center) Seismic and code upgrades C 10,933   12,184 19,533
Monterey Peninsula (Fort Ord Center) New public safety center W 289   9,223 18,316
Reedley New child development center C 302   10,241 12,716
Totals     $94,835   $191,648 $372,222
a Community college districts typically issue local general obligation bonds to pay for a share of project costs.  
b Extension of liquidation period for funds initially provided in the 2020-21 Budget Act. That budget act provided $1.6 million for preliminary plans and working drawings, some of which is still available to cover the remaining cost of preliminary plans.
c Extension of liquidation period for funds initially provided in the 2020-21 Budget Act. That budget act provided $1.5 million for preliminary plans and working drawings, some of which is still available to cover the remaining cost of working drawings.
d Extension of liquidation period for funds initially provided in the 2020-21 Budget Act. That budget act provided $1.1 million for preliminary plans and working drawings, some of which is still available to cover the remaining cost of preliminary plans.