Introduction
			A partnership between the state and the private sector is 
			sometimes used to finance, design, construct, operate, and maintain 
			state infrastructure projects (such as highways, mass transportation 
			systems, and state buildings). Such a P3 requires the state and the 
			private sector to collaborate when making decisions about a project. 
			By bringing external resources and specialized expertise to a 
			project, the state is expected to achieve certain benefits from a P3 
			that typically are not achievable when using a more traditional, 
			public sector procurement approach. 
			In recent years, California has entered into P3s with private 
			partners for two state infrastructure projects. Specifically, to 
			build and operate the Presidio Parkway transportation project in San 
			Francisco (also known as Doyle Drive) and to build and maintain a 
			new courthouse in Long Beach. Each of these agreements is for a 
			period of about 30 years. The combined estimated cost to the state 
			for both of these projects is about $3.4 billion. Given their 
			significant cost and the limited experience the state has had in 
			such partnerships, we identify in this report best practices for the 
			state to follow when using P3s and present recommendations for 
			maximizing the benefits to the state. In preparing this report, we 
			met with representatives from various state departments about their 
			experiences with P3s, as well as numerous P3 experts. We also 
			reviewed the literature regarding best practices for implementing 
			such partnerships. 
			Background
			State Procures Infrastructure Projects in Various Ways
			 State law specifies the processes for reviewing and approving 
			proposed state infrastructure projects. In most instances, such as 
			for court facilities and state office buildings, the Legislature 
			must approve and appropriate funds for a state project. (They also 
			must receive approval from the State Public Works Board at various 
			subsequent stages.) However, the California Transportation 
			Commission (CTC) approves most state projects related to 
			transportation. The review and approval process for state projects 
			generally involves determining (1) the need for the project, (2) how 
			the project fits into existing infrastructure systems, (3) the 
			project's priority relative to other state infrastructure projects, 
			and (4) how the project will be funded. This process typically 
			consists of multiple reviews and approvals as a project's 
			development moves from concept to environmental review and 
			preliminary engineering, and then to design and construction. 
			State law specifies three general types of procurement 
			approaches—design–bid–build, design–build, and P3—that state 
			departments can use to deliver infrastructure projects that have 
			been approved for construction. As summarized in Figure 1, each of 
			these procurement approaches involves varying ways of contracting
			with the private sector for a project. We discuss each approach 
			in more detail below.
			
				 
			 
			Design–bid–build. State departments can 
			use a design–bid–build approach to procure all types and sizes of 
			infrastructure. Under this approach, the work for each stage of a 
			project is performed separately. For example, a state department 
			will generally first award an architectural/engineering contract to 
			design the project based on subjective criteria of qualifications 
			and experience of the architect/engineer. In some cases, however, 
			state staff may design the project. After detailed project plans and 
			drawings are completed, the department then selects a contractor to 
			perform the construction work. Construction contracts are awarded 
			objectively based on competitive bidding, with the contract going to 
			the qualified bidder who submits the lowest price. Once construction 
			is completed, the state department is responsible for operating and 
			maintaining the facility. The state pays for the cost of 
			design–bid–build projects either up front with state funds or over 
			time by selling general obligation bonds or lease–revenue bonds. 
			Design–build. Under existing state law, 
			certain departments can use design–build procurement. With 
			design–build, the department typically contracts with a private 
			general contractor to both design and build the infrastructure 
			project. The department does not separately contract with an 
			architect/engineer for design. Rather, the general contractor is 
			responsible for subcontracting with other entities for design and 
			various construction work. The state awards a design–build contract 
			through a competitive bidding process that evaluates factors such as 
			price, design features, construction schedule, and community or 
			environmental outcomes. Under design–build, the state maintains 
			responsibility for financing, operating, and maintaining the 
			project. 
			Alternatively, another type of design–build involves the state 
			transferring design and construction risks to a specialized 
			construction manager, rather than a general contractor. This 
			approach is commonly referred to as "construction manager at risk 
			procurement." With construction manager at risk, the state awards a 
			contract based on a fee. The construction manager designs the 
			project and solicits bids from subcontractors and suppliers. The sum 
			of these bids, along with a surcharge, determines the total price 
			the state pays for the project. 
			P3s. Current state law authorizes three 
			state departments—Caltrans, AOC, and the High–Speed Rail Authority 
			(HSRA)—to use some form of a P3. While there can be varying degrees 
			of P3s, the type of P3 often discussed and most recently used in 
			California is when a single contract is entered into with a private 
			partner (often a consortium of several companies) for the design, 
			construction, finance, operation, and maintenance of an 
			infrastructure facility. For the purpose of this report, we 
			generally define a P3 as the contracting with the private sector to 
			design–build–finance–operate–maintain an infrastructure project. (As 
			we discuss in the nearby box, the state can also enter into 
			partnerships with other public entities, such as counties, for the 
			procurement of state infrastructure.)
			
			
			State Partnerships with Other Public Entities
				In addition to the private sector, the state can utilize 
				other public entities (such as a county or other public 
				authorities) for the design, construction, operation, and 
				maintenance of an infrastructure project. In such cases, 
				however, these entities typically subcontract (either through a 
				single contract or multiple contracts) with the private sector 
				to perform much of the actual work on a project. For example, 
				the public partner could finance a project with municipal 
				financing, contract with a private company for design and 
				construction work, and have separate contracts with other 
				companies to maintain and operate the infrastructure facility. 
				An example of a public–public partnership project is "The 
				Toll Roads" in Southern California—a 50 mile network of tolled 
				state highways in southern Orange County built by the 
				Transportation Corridor Agencies (TCAs), which are led by 
				locally elected officials. In 1987, the Legislature authorized 
				the TCAs to design, construct, finance, operate, and maintain a 
				portion of the state's highways and to fund the cost of the 
				project with tolls. The TCAs contracted with private companies 
				to perform most of the work on the project.
			 
			
			Under a P3 approach, the state can transfer a significant amount 
			of responsibility associated with a project to the private sector. 
			For example, the private partner will generally make design and 
			construction decisions and be responsible for paying the costs to 
			resolve any construction issues in order to ensure that the project 
			is completed on time. In addition, the partner will often be 
			required to finance the project, which generally includes the costs 
			of design and construction staff, materials, and construction 
			equipment. However, in order for a private partner to be willing to 
			finance these costs, the contract must specify a mechanism for 
			repaying the partner. In many cases, this involves a revenue source 
			created by the project (such as a toll or user fee on the 
			infrastructure facility), with the private partner taking on the 
			risk that the projected revenues will materialize at the level 
			anticipated. Alternatively, the state can commit to making annual 
			payments to the partner from an identified funding source, such as 
			tax revenues. Since it can take many years for a revenue source 
			(such as a toll on a road) to pay off the private financings, the 
			terms of P3 contracts generally range between 25 years to 100 years. 
			The P3 procurement approach is typically more complex than 
			design–bid–build and design–build. For instance, under a P3 
			approach, the state must first evaluate a pool of potential bidders 
			to determine if they have the qualifications necessary to design, 
			build, finance, operate, and maintain the infrastructure facility. 
			Then, qualified bidders submit proposals that the state evaluates in 
			order to select a preferred bidder. A P3 contract is often awarded 
			to the bidder deemed to provide the best value.
			Three State Departments Authorized to Use P3s for 
			Certain Projects
			As shown in Figure 2, existing state law authorizes the use of 
			P3s for certain transportation and court construction projects. 
			(State law also authorizes certain local governments to use P3s for 
			local infrastructure projects.) Below, we discuss in more detail the 
			specific P3 authority provided to state departments. 
		
			Figure 2
			Summary of State Public–Private 
			Partnership (P3) Authority
			
				
					
					
					
					
					
				
				
					
						| State Department | Type of 
							Infrastructure | State 
							Law | Brief 
							Description | 
							Projects To Date | 
					
						| Caltrans | Highways | Chapter 107, Statutes of 
							1989 (AB 680, Baker) | Allowed Caltrans to enter 
							into up to four P3s. | State Route (SR) 91 and SR 
							125 | 
					
						| Caltrans and regional 
							transportation agencies | Highways, local roads, and 
							transit | Chapter 2, Statutes of 2009 
							(SB 2X 4, Cogdill)a | Allows Caltrans and regional 
							agencies to enter into an unlimited number of P3s 
							through 2016. | Presidio Parkway | 
					
						| High–Speed Rail Authority 
							(HSRA) | High–Speed rail | Chapter 796, Statutes of 
							1996 (SB 1420, Kopp) | Allows HSRA to enter into P3 
							contracts for the proposed rail system. | High–Speed train system | 
					
						| Administrative Office of the 
							Courts (AOC) | Court facilities | Chapter 176, Statutes of 
							2007 (SB 82, Committee on Budget and Fiscal Review) | Establishes process for 
							review of AOC P3 projects. | Long Beach Courthouse | 
					
						
					
				
			
			
		 			
			
			Caltrans. Chapter 107, Statutes of 1989 
			(AB 680, Baker), authorized Caltrans to enter into P3 agreements for 
			up to four projects. Under this authorization, as well as that 
			provided in related follow–up legislation, Caltrans built ten miles 
			of tolled express lanes in the median of the existing State Route 
			(SR) 91 in Orange County. In addition, the department built SR 125 
			in San Diego County that connects the area near the Otay Mesa border 
			crossing with the state highway system. For each project, Caltrans 
			used a single contract with a private partner to design, construct, 
			finance, operate, and maintain the facility. (We discuss these two 
			projects in more detail later in this report.)
			In 2009, Caltrans' authority to enter into P3 agreements was 
			expanded. Specifically, Chapter 2, Statutes of 2009 (SB 2X 4, 
			Cogdill), authorizes Caltrans and regional transportation agencies 
			(such as the Los Angeles County Metropolitan Transportation 
			Authority) to enter into an unlimited number of P3 agreements for a 
			broad range of highway, road, and transit projects through December 
			31, 2016. However, the legislation specifies that such P3 projects 
			must achieve one or more objectives as determined by the CTC, which 
			is responsible for programming and allocating funds for the 
			construction of highway, rail, and transit improvements. These 
			objectives include:
			
				- 
				Improve travel times or reduce vehicle hours 
			of delay.
				
- 
				Improve transportation operation or safety.
				
- 
				Provide quantifiable air quality benefits.
				
- 
				Meet a forecasted demand of transportation.
				
In addition, the above agreements are subject to a 60–day review 
			by the Legislature and PIAC before Caltrans can sign them. The PIAC 
			is an advisory commission created by Chapter 2 and chaired by the 
			Secretary of the Business, Transportation, and Housing (BT&H) 
			Agency. Specifically, PIAC is charged with assembling research, best 
			practices, and lessons learned from transportation P3s around the 
			world. The commission can, upon request, assist Caltrans and 
			regional transportation agencies with P3 project selection, 
			evaluation, procurement, and implementation. Currently, PIAC 
			consists of about 20 volunteer members and is staffed within 
			existing BT&H Agency resources.
			In January 2011, Caltrans entered into its first P3 under Chapter 
			2 for the Presidio Parkway project. This particular P3 requires the 
			private partner to complete the second phase of the design and 
			reconstruction of the southern approach to the Golden Gate Bridge 
			and to operate and maintain the roadway for 30 years. In exchange, 
			the state will make payments estimated to total roughly $1.1 billion 
			to the private partner over the life of the contract. 
			Judicial Council and AOC. Under current 
			law, the judicial branch is authorized to use P3s. In addition, 
			state law requires the Judicial Council (the policy making body for 
			the judicial branch) and their staff in the AOC to develop 
			performance standards to facilitate the review of P3s and requires 
			the Department of Finance (DOF) to review projects that include a P3 
			component. The legislation also specifies that AOC may only proceed 
			with a P3 if the Legislature does not object to the performance 
			standards adopted for the project. 
			The 2007–08 Budget Act directed AOC to gather 
			information regarding the possible use of a P3 for the replacement 
			of the Long Beach courthouse. In December 2010, AOC entered into a 
			P3 that requires a private developer to finance, design, build, 
			operate, and maintain the Long Beach courthouse over a 35–year 
			period in exchange for payments from the state totaling $2.3 
			billion. At this time, the Long Beach courthouse is the only project 
			that the AOC has procured using a P3. 
			The HSRA. Chapter 796, Statutes of 1996 
			(SB 1420, Kopp), created the HSRA and authorized it to use P3 
			procurement for the development of a High–Speed train system 
			connecting northern and southern California. However, state law does 
			not establish a specific process for reviewing or approving P3s for 
			HSRA. State law requires capital expenditures by HSRA to be approved 
			by the Legislature. Based on the authority's 2012 business plan, the 
			HSRA would not award its first P3 contract until 2023. 
			Benefits and Limitations of P3s 
			Government entities typically use P3s to achieve benefits that 
			they may not be able to obtain under a more traditional procurement 
			approach (such as design–bid–build). However, P3s can also introduce 
			new limitations and costs as summarized in Figure 3 and described in 
			detail below. 
						
			
			Potential P3 Benefits 
			Transfers Project Risks to Private Partner. 
			The P3s can transfer risks associated with a project from a 
			government entity to a private partner. Figure 4 summarizes the 
			major risks that could potentially be transferred, such as those 
			related to financing, operation, and maintenance. As indicated in 
			the figure, the most significant risks are associated with the 
			design and construction of a project. For example, under a P3 
			approach, the private developer would bear the risks and costs if 
			the design of the project were changed to fit certain site 
			conditions (such as soil quality or the discovery of archeological 
			artifacts). Similarly, the private partner would be responsible for 
			project cost overruns, which can be very expensive. The transfer of 
			this risk could reduce or eliminate the need for additional public 
			funds to complete a project. Moreover, the partner would bear the 
			risk if the actual revenue collected from any tolls or user fees are 
			less than projected, which depending on the project, can be 
			significant. In order to ensure adequate compensation, private 
			developers attempt to estimate the anticipated costs of resolving 
			issues on the risks they assume and factor these costs into their 
			bid. However, in some cases, the developer may be better equipped to 
			manage certain risks at a lower cost than if the government retained 
			all of the project risks.
			
				 
			 			
			
			Greater Price and Schedule Certainty. 
			Based on a survey conducted by the Federal Highway Administration 
			(FHWA), governments around the world reported that P3s can provide 
			better price and schedule certainty for the design and construction 
			of a project compared to a more traditional procurement approach 
			(such as design–bid–build). In part, this is because P3s allow a 
			government entity to share certain risks with a private developer 
			who has more experience with a particular type of project and has 
			developed strategies to mitigate potential cost increases that could 
			result from such risks. The government can also achieve greater 
			price certainty from P3s because, as is the case with design–build 
			and construction manager at risk contracts, the contacts often have 
			a maximum price. This means that the private partner must pay for 
			any cost increases above the agreed upon price. In addition, the 
			government typically sets up a streamlined process to review the 
			design and construction decisions made by the partner, which can 
			help prevent delays in the project schedule. Moreover, P3s that 
			include financing can incentivize the partner to complete the 
			project on time and receive the necessary funding (such as payments 
			from the government or revenues from project user fees) to repay the 
			private loans taken out to finance the project.
			More Innovative Design and Construction Techniques. 
			Experts in P3s generally believe that the private sector is often 
			better able to develop innovative project designs and construction 
			techniques than government entities. In part, this may be due to the 
			specialized expertise that a private partner can bring to a project. 
			Greater design and construction innovation could result in a variety 
			of potential benefits, including lower project costs, a higher 
			quality project, shorter construction schedules, and enhanced 
			project features. 
			"Free Up" Public Funds for Other Purposes. 
			In general, using a private developer's access to capital can free 
			up government funds to advance the construction of other 
			infrastructure in the near–term and, thus, provide the public with 
			access to improved infrastructure sooner than planned. In addition, 
			the developer's financing can sometimes provide more advantageous 
			repayment terms than a government might typically obtain under a 
			more traditional public financing approach. For example, if 
			repayment were extended over a longer period of time than the 
			government typically has to repay borrowed funds, it could reduce 
			the amount that must be repaid each year. Such freed–up public funds 
			could then be allocated for other purposes. 
			Quicker Access to Financing for Projects. 
			In addition, by making a private developer responsible for financing 
			a particular project, a government might be able to access financing 
			in cases where it does not yet have the authority to borrow. For 
			example, California's constitution requires voter approval prior to 
			selling certain types of bonds to finance infrastructure projects, 
			which could delay the state from accessing financing for certain 
			projects. However, projects financed through a P3 would not require 
			voter approval, potentially allowing some projects to start 
			construction sooner.
			Higher Level of Maintenance. Due to 
			insufficient funding for maintenance, as well as how existing 
			maintenance funding is prioritized, some governments currently do a 
			poor job in maintaining their infrastructure. For example, due to a 
			lack of regular maintenance, only 28 percent of California's 
			highways are in good condition. As a result, many highways require 
			costly major rehabilitation or replacement. Under a P3 approach, a 
			government could require the private partner to maintain the 
			constructed infrastructure to specified standards. Essentially, this 
			means that P3 facilities could remain in good condition over longer 
			periods of time, thus allowing the government to delay the cost of 
			major rehabilitation or replacement. 
			Keeps Project Debts Off the Government's "Books." 
			Another benefit of P3 financing is that the debt incurred by a 
			private partner for a project may not be counted as government debt. 
			In other words, P3 financing may not appear as debt on government 
			balance sheets. According to recent studies by the FHWA and the 
			United Nations Economic Commission for Europe, this is one of the 
			reasons why some countries in the European Union have chosen to use 
			P3s. While the benefit of debt not appearing on the government's 
			balance sheet is probably more important to governments subject to 
			strict limitations on debt, it could also improve the overall 
			ability of some governments to borrow funds for other purposes. 
			However, since California does not have such strict debt limitations 
			that restrict its options for financing infrastructure projects this 
			benefit does not currently apply to the state.
			Potential P3 Limitations
			Increased Financing Costs. Financing a 
			project through a P3 is likely to be more expensive than the 
			financing options typically used under the more traditional 
			procurement approaches (such as obtaining state and federal loans). 
			This is because private companies typically pay higher interest 
			rates than government entities to borrow money. For example, a study 
			of P3 projects in Canada found that private partners typically pay 1 
			percentage point higher on loans compared to the governmental cost 
			of borrowing. In times of limited access to financial markets (such 
			as the financial crisis of 2008), the cost difference between 
			private and public borrowing was 2 percentage to 3 percentage 
			points. In addition, private companies will often seek to earn a 
			profit of roughly 10 percent to 25 percent when loaning funds to a 
			government, which can further increase P3 financing costs.
			Greater Possibility for Unforeseen Challenges. 
			As previously discussed, in comparison to design–bid–build and 
			design–build contracts, P3 contracts cover a much longer time period 
			and scope of activities (such as maintenance of the infrastructure 
			facility). Thus, there is a greater possibility for unforeseen 
			issues to arise under a P3 approach. Such issues could include 
			disputes regarding certain terms in the contract, as well as the 
			private partner being acquired by another company or going out of 
			business, effectively resulting in project schedule delays and 
			additional costs to the government. 
			Limits government's Flexibility. The 
			long–term nature of P3s can also "lock in" certain government 
			funding priorities based on operational needs determined at the time 
			the contract is negotiated. This can make it difficult to change 
			funding allocations to reflect changes in government priorities. For 
			example, a P3 contract may require litter and graffiti to be removed 
			from a highway within three days. Renegotiating the terms of this 
			contract to use the funds designated for prompt litter and graffiti 
			removal to support another activity or project could be very 
			difficult. In addition, by bundling multiple phases of a project 
			into a single contract, P3s can make it more difficult for the 
			government to change how a project is managed. For example, if the 
			government wanted to make changes to how a private partner handled 
			customer complaints and questions on a toll road, it would likely 
			need to propose amendments to the contract, which could increase the 
			project's overall cost. 
			New Risks From Complex Procurement Process. 
			As discussed earlier, the procurement process for P3s is more 
			complex than the procurement processes traditionally used for state 
			infrastructure projects (such as design–bid–build and design–build). 
			In addition to a project's design, construction price, and schedule, 
			under P3 approach, the government entity must also evaluate 
			proposals based on financing, operations, and maintenance. In 
			addition, P3 procurements can also involve complex negotiations 
			between the government and the private developers who bid on the 
			project. As a result, P3s can require the government to perform new 
			activities and take on certain risks that it may not be experienced 
			at handling. For example, if the state does a poor job of drafting 
			agreements or fails to address relevant issues in these agreements, 
			it could experience unexpected costs or receive lower levels of 
			service than planned. 
			Fewer Bidders. According to the 
			research, infrastructure projects that are relatively expensive and 
			complex tend to be more ideal candidates for P3s. In addition, 
			private partners tend to be comprised of multiple companies who 
			coordinate efforts to develop a P3 bid—each with expertise in a 
			particular component of the project (such as design and 
			construction, financing, or maintenance). As a result, few private 
			developers have the financial resources and technical skills to 
			compete for P3 projects, especially on their own. According to 
			experts, P3 projects typically receive between one and three bids. 
			In comparison, similarly sized projects procured under traditional 
			public sector approaches typically receive a greater number of bids. 
			Less competition for a project procured as a P3 could be detrimental 
			to the government, as more competition for a project generally 
			reduces the price of a project while increasing its quality. 
			Some Benefits Achieved to Date
			In order to determine whether the state has achieved some of the 
			intended benefits of P3s, we reviewed the two completed P3 projects 
			procured by the state'sR 91 Express Lanes and SR 125 Tollway. At the 
			time of this analysis, however, Caltrans was unable to provide us 
			with the necessary data to evaluate whether the P3 projects 
			completed by the state—SR 91 and SR 125—resulted in greater price 
			and schedule certainty than if the projects were procured under a 
			more traditional approach. As a result, we reviewed recent state 
			projects that, while not considered P3s, transferred certain risks 
			and responsibilities to the private sector. Specifically, we 
			reviewed those projects procured under design–build and construction 
			manager at risk contracts. These particular projects are summarized 
			in Figure 5.
		
			Figure 5
			Design–build and Construction Manager 
			at Risk: Cost and Schedule Outcomes
			
				
					
					
					
					
					
				
				
					
						| Project | 
							Implementing Agency | Type of 
							Procurement | 
							Project Completion | 
							Percentage Price Increase From Contracta | 
					
						| SR 73 Toll Road | TCAs | design–build | 4 months early | — | 
					
						| SR 241, SR 261, and SR 133 
							Toll Roads | TCAs | design–build | 14 months early | — | 
					
						| SR 22 Carpool lanes | OCTA | design–build | 1 week late | 4.6% | 
					
						| Contra Costa Justice Center | AOC | Construction manager at risk | 1 week early | 
							1.2 | 
					
						| Fresno Court Facility 
							Renovation | AOC | Construction manager at risk | 1 month late | 0.2  | 
					
						| State Office Building in 
							Oakland | DGS | design–build | On schedule | — | 
					
						| San Francisco Civil Center | DGS | design–build | On schedule | 1.2  | 
					
						| State Office Building in Los 
							Angeles | DGS | design–build | 3 months late | 7.3  | 
					
						| State Office Buildings in 
							Sacramento | DGS | design–build | On schedule | 10.4  | 
					
						| Caltrans Office Building in 
							Los Angeles | DGS | design–build | 15 months late | 5.2 | 
					
						| Caltrans Office Building in 
							Marysville | DGS | design–build | On schedule | 3.0 | 
					
						| Central Plant Renovation in 
							Sacramento | DGS | design–build | 4 months late | 0.6 | 
					
						
					
				
			
			
		 			
			
			Price and Schedule Certainty Generally Achieved. 
			In terms of the projects reviewed, most of them were generally 
			successful at staying on budget and schedule. When there were 
			schedule and cost overruns, they were typically relatively small. 
			For example, three–fourths of the projects opened to users on 
			schedule or within one month of the planned deadline. Three–fourths 
			of the projects were also completed on budget or with less than 5 
			percent in cost overruns. While there is no way of knowing what the 
			price and schedule outcomes would have been if these projects were 
			procured differently (such as a design–bid–build project), the 
			projects were generally successful at meeting the goal of price and 
			schedule certainty. 
			Mixed Results During Operations. The SR 
			91 Express Lanes and the SR 125 Tollway both experienced problems 
			during the operational phases of their P3 contracts. Specifically, 
			while both facilities remained open to the public, Caltrans incurred 
			additional costs resulting from disputes with its private partners. 
			For example, the SR 91 contract contained a "non–compete clause" 
			that prohibited Caltrans or other public agencies from competing 
			with the tolled lanes built by the private partner. Thus, if public 
			agencies made any improvements to transportation facilities in the 
			SR 91 corridor (including minor projects to improve the safety of 
			the general–purpose lanes of the highway), the private partner 
			believed that the state would be required to compensate for the loss 
			of toll revenue if fewer people drove on the tolled P3 lanes due to 
			these improvements. The issue was litigated in court, but was 
			ultimately settled when the private partner agreed to sell the 
			rights of the express lanes to the Orange County Transportation 
			Authority (OCTA), a local public transportation agency. Since OCTA 
			assumed control of SR 91, Caltrans has not had any conflicts 
			regarding the non–compete clause. 
			The SR 125 project experienced legal challenges that delayed its 
			completion. Such challenges made the partnership less profitable for 
			the private partner. Specifically, the lawsuit alleged that 
			Caltrans, as a partner in the agreement, was partially liable for 
			losses claimed by some of the private companies involved in the 
			project. The private partner ultimately declared bankruptcy, with 
			the court awarding the rights to the remainder of the P3 to a group 
			of lenders who had financed the project. This group subsequently 
			sold the agreement to the San Diego Association of Governments. 
			Given the nature of design–build and construction manager at risk 
			contracts, the other projects we reviewed did not transfer 
			responsibility for operating the infrastructure facility to a 
			private partner after it was built. However, the toll road projects 
			involving SR 73, SR 241, SR 261, and SR 133 did involve other public 
			entities being responsible for operating the facilities. This 
			network of tolled public highways in Orange County (commonly 
			referred to as "The Toll Roads") are managed by the Transportation 
			Corridor Agencies (TCAs), which are public agencies led by locally 
			elected officials. While the TCAs may contract with private 
			companies to operate the toll roads, they are ultimately responsible 
			for making key decisions and directly managing the contracts. When 
			the TCAs encountered problems after the highways became operational, 
			they were able to end a contract with a private operator who was not 
			meeting expectations and later rebid the work to a different 
			company. Using separate contracts and retaining more responsibility 
			for making key decisions helped avoid some of the unforeseen costs 
			(such as legal costs) that were incurred with the state's P3 
			projects. 
			P3 Best Practices
			As part of our examination of the P3 approach, we reviewed 
			international research and interviewed experts in the field. Based 
			on our review, we identified a set of best practices that have been 
			found to maximize the potential benefits of P3s and minimize its 
			potential limitations. These best practices are summarized in Figure 
			6 and discussed in more detail below.
	
							
		
			Establish Overall P3 Policy and Implement Transparent 
			Processes 
			Experts recommend that governments adopt an overall P3 policy to 
			(1) guide decision–makers when evaluating different procurement 
			options and (2) inform potential private partners and the public of 
			the process. For example, experts recommend having a transparent 
			process so that potential partners are aware of the specific 
			requirements that must be satisfied to bid on a project and how long 
			the procurement process will likely take. Such transparency also 
			helps stakeholders and the public understand how and why a 
			government entity selected a private company to build or operate 
			public infrastructure. For example, Virginia created the Office of 
			Transportation public–private Partnerships to develop a consistent 
			institutionalized process for P3 procurements, in order to help 
			attract qualified developers and contractors.
			Adopt Criteria to Determine Good Candidates for P3 
			Projects
			International research also finds that it is good practice for 
			governments to adopt criteria for determining whether projects would 
			be a good fit for P3 procurement, as not all public infrastructure 
			projects would benefit from a P3 approach. For example, as we 
			discuss later in this report, the Legislature could establish 
			criteria that provide a reasonable means of screening potential P3 
			projects. Such criteria should not be too prescriptive or 
			cumbersome. Experts recommend that the screening criteria include 
			the following:
			
				- Government Benefit From Using 
				Nonpublic Financing. The screening process should 
				determine if there is a benefit (such as completing the project 
				sooner) to the government from financing the project with a private 
				partner, rather than using public funds upfront to pay for the 
				project. Typically, relatively expensive projects—with costs 
				ranging from the hundreds of millions to billions of dollars—are 
				more likely to benefit from private financing, as it can take 
				several years to save up enough funds to build a large project 
				without financing or to get approvals for public financing. 
- Technically Complex. 
				Generally, projects that are technically complex are more likely to 
				benefit from the innovation or specialized expertise that is 
				typically associated with P3s. For example, a private partner with 
				extensive experience designing and building tunnels or bridges may 
				be able to construct a complex tunnel or bridge more quickly and/or 
				at a lower cost. On the other hand, projects that are very simple 
				(such as repaving a road) are not as well suited for the P3 approach 
				because they are less likely to benefit from innovation and 
				specialized expertise.
- Ability to Transfer Risks to 
				Partner. Projects that are good candidates for P3s 
				generally have significant known risks that the government can 
				transfer to a private partner. For example, a project that is in the 
				very early stages of development and does not have a completed 
				environmental review may lack sufficient information to allow for an 
				effective transfer of risk. Given these unknown risks, potential 
				partners may be hesitant to bid on the project or may incorporate 
				large premiums into their bid. Alternatively, a project with clearly 
				identified risks (such as if a toll road will generate enough 
				revenue to finance the project) would be more well–suited as a P3. 
- Revenue Source to Repay Financing. 
				As discussed above, P3s require a revenue source to repay the 
				financing provided by the private partner. Ideally, a project would 
				have a dedicated revenue source (such as a toll or user fee) to 
				repay the money borrowed from the partner. The government entity, 
				however, could commit to make payments to the partner from 
				government funding sources, such as tax revenues.
Conduct a Rigorous Value for Money Analysis
			Once it is determined that a particular project is a good P3 
			candidate, experts recommend that the government entity perform a 
			detailed analysis that compares the project's costs using a P3 to 
			using a more traditional procurement approach. A commonly used 
			analysis is a "value for money" (VFM) analysis, which identifies all 
			the costs of a project (such as the design, construction, and 
			operation and maintenance of the facility) over the life of the 
			project or the term of the lease with the private partner. These 
			costs are then "discounted" over time to determine the project's 
			cost in net present value. In other words, because the expenditures 
			take place over several decades and the timing of the expenditures 
			differ between a P3 approach and the more traditional procurement 
			approach, the comparisons are adjusted to account for the fact that 
			money available at the present time is worth more than money 
			available in the future. Specifically, the VFM analysis should 
			compare the cost of the different procurement approaches in net 
			present value terms of delivering the same level of service—both 
			in terms of the quality of the infrastructure constructed and the 
			quality of the maintenance and operation services provided. 
			The VFM analyses can be complex and the underlying assumptions 
			can significantly influence the outcomes. Thus, most experts 
			recommend specifying parameters for the assumptions (such as for the 
			discount rate) so that all potential projects are evaluated with 
			similar criteria. 
			Adopt and Implement Project Approval Process
			Experts recommend maintaining a process to approve projects for 
			P3 procurement that allows good candidates to proceed. The approving 
			entity (such as the Legislature or an independent board), which is 
			typically separate from the agency sponsoring the project, should 
			verify that (1) the project satisfies most of the established P3 
			criteria and (2) the VFM analysis shows that a P3 procurement is the 
			best option. In addition, P3 experts recommend obtaining project 
			approval prior to having potential partners bid on the project. This 
			is because private developers may not bid on a project if they are 
			unsure whether the approving entity might stop it from moving 
			forward. 
			Establish Government Expertise in P3s
			Another P3 best practice is for government entities to develop 
			expertise regarding P3s, in order to better protect public resources 
			when entering into large contracts with private partners. 
			Experienced departmental staff can make it easier for the state to 
			handle P3 workload quickly and thoroughly, as well as effectively 
			communicate with the private sector. Governments could use private 
			consultants to help with this workload. 
			Our research also found that P3 expertise can reside at multiple 
			levels of government. For example, PPP Canada provides information 
			and assistance to Canada's provincial and municipal governments on 
			the use of P3s. At the provincial level, Partnerships BC in British 
			Columbia provides specialized services, such as managing projects 
			and facilitating communication with the private sector. In addition, 
			experts recommend reviewing the outcomes of P3 projects at various 
			stages to allow a government entity to determine what worked well 
			and what problems were encountered on each project. The lessons 
			learned can be used to inform future P3 procurements. 
			State's Use of P3s Falls Short of Best Practices
			As we discussed earlier in this report, existing state law 
			authorizes Caltrans, AOC, and the HSRA to use P3s to procure certain 
			types of infrastructure. In analyzing their use of this authority, 
			we generally found that the practices of Caltrans and AOC are not 
			necessarily aligned with P3 best practices. (At the time of this 
			report, HSRA had not entered into any P3 contracts.) For example, 
			our analysis indicates that these departments did not use clear P3 
			processes and appear to have selected projects not well suited for a 
			P3 procurement—meaning the Presidio Parkway project and the Long 
			Beach courthouse project. Our findings regarding each of these 
			projects are summarized in Figure 7 and described in detail below. 
								
			
			State Lacks Transparent P3 Processes
			As discussed above, having clearly defined and transparent P3 
			processes is considered a best practice. However, our review found 
			that the state's use of P3 procurement for the Presidio Parkway and 
			Long Beach courthouse projects lacked transparent frameworks and 
			clear processes. For example, when 
			Caltrans used a P3 procurement for the Presidio Parkway, the 
			department lacked a transparent framework for selecting the project 
			and conducting a VFM analysis. It did not release a draft P3 program 
			guide until December 2011, one year after signing the agreement for 
			Presidio Parkway. While the guide addresses many procedural 
			questions regarding the department's future use of P3s, it does not 
			establish a consistent process for evaluating potential P3 projects 
			through the use of a VFM analysis. We think this is a significant 
			shortcoming of the guide because establishing VFM processes and 
			parameters is important to ensure that projects are evaluated on a 
			consistent basis using reasonable assumptions. The Caltrans draft P3 
			program guide also does not address how project evaluation, review, 
			and procurement responsibilities will be carried out when the state 
			partners with local transportation agencies. Specifically, the guide 
			does not lay out how the lead agency will be determined and which 
			entity is responsible for certain tasks, such as review and 
			oversight. As a result, various local agencies that we talked to 
			appear to have different understandings of what will be required of 
			them for P3 projects. 
			Similarly, AOC did not use a transparent framework in selecting 
			the Long Beach courthouse to be a P3 project. For example, AOC did 
			not develop guidelines for selecting potential P3 projects and 
			conducting VFM analyses. More importantly, at the time of this 
			report, AOC had not developed transparent criteria or processes for 
			determining potential P3 projects in the future. For example, it is 
			unclear how AOC will identify projects that are likely to benefit 
			from a P3 approach and evaluate potential projects through the use 
			of VFM analyses. 
			Selection Criteria for Recent Projects Not Aligned to 
			Best Practices
			Our analysis indicates that the processes used to identify the 
			two recent state projects for P3 procurement—the Presidio Parkway 
			and the Long Beach courthouse—included few of the best practice 
			criteria. 
			Presidio Parkway Selection Was Problematic. 
			According to Caltrans staff, the Presidio Parkway project was 
			selected as a P3 candidate primarily based on two criteria: (1) an 
			estimated project cost of more than $100 million and (2) a completed 
			environmental impact review. However, according to the identified 
			best practices, these two factors alone do not constitute a robust 
			set of screening criteria. In other words, the selection process for 
			the project did not include such recommended criteria as the ability 
			to transfer risk to the private sector and whether the state would 
			benefit from using non–state financing. While the selection process 
			for a P3 project does not need to include all of the best practice 
			criteria, including such criteria does help ensure that the intended 
			P3 benefits are achieved. Our analysis indicates that if Caltrans 
			utilized such criteria in its selection process, the Presidio 
			Parkway project would have been found to be inappropriate for P3 
			procurement. 
			For example, the Presidio Parkway project was too far along to 
			transfer many of the project's risks to a private partner. This is 
			because the Presidio Parkway's first phase of construction was 
			already underway using a design–bid–build procurement when the 
			second phase of the project was selected for P3 procurement. As a 
			result, potential private partners had limited access to the 
			construction site, which in turn made them less willing to take on 
			many of the project's construction risks. For example, the state 
			retained significant risks regarding the discovery of archeological 
			artifacts and endangered species. In addition, Caltrans had already 
			designed about half of the project's second phase prior to awarding 
			the P3 contract. Thus, the winning bidder may be limited in its 
			ability to find cost–savings through innovative design and 
			construction techniques because it must adhere to certain 
			specifications it did not design.
			Long Beach Courthouse Selection Was Problematic. 
			According to AOC staff, the Long Beach courthouse project was 
			selected as a P3 candidate based primarily on two criteria: (1) it 
			was one of the largest court construction projects considered at 
			that time and (2) the Long Beach area has a competitive market for 
			the type of property management staff needed to operate a P3. 
			Similar to the selection of the Presidio Parkway project, the 
			selection process for the Long Beach courthouse project did not 
			include much of the recommended best practice criteria. For example, 
			the selection process did not evaluate whether the project is 
			technically complex. While the ideal level of complexity for a P3 is 
			difficult to define in specific terms, the Long Beach courthouse 
			project lacks unique or complex features that would likely benefit 
			from innovative design and construction techniques. Accordingly, our 
			analysis indicates that if AOC utilized best practice criteria in 
			its selection process, the Long Beach courthouse project would have 
			been found to be inappropriate for P3 procurement. 
			VFM Analyses Based on Assumptions That Favored P3 
			Procurement 
			As described above, VFM analyses can help decision–makers compare 
			the cost of a project under different procurement options. Both 
			Caltrans and AOC contracted with private consultants to perform such 
			analyses for the Presidio Parkway and Long Beach courthouse 
			projects. Specifically, the analyses compared the costs of 
			constructing the project under a more traditional approach to a P3 
			approach. The VFM analyses found that the state would benefit 
			financially if the Presidio Parkway and Long Beach courthouse 
			projects were procured as P3s—meaning it would be cheaper to have a 
			private developer build and operate the planned facility. Our review 
			of these particular analyses, however, indicates that both VFM 
			analyses were based on several assumptions that are subject to 
			significant uncertainty and interpretation and tended to favor a P3 
			procurement. If a series of different assumptions were made, the VFM 
			analyses would have shown that the P3 procurement on the Presidio 
			Parkway and Long Beach courthouse projects would be more expensive 
			in the long run than a more traditional procurement. 
			Assumptions in Presidio Parkway Analysis Favored P3. 
			Some of the key assumptions made by Caltrans in the VFM analysis of 
			the Presidio Parkway project that tended to favor P3 procurement 
			include: 
			Relatively High Discount Rate. 
			In order to calculate the net present cost of the project, Caltrans' 
			VFM analysis discounts the cost of the project under a traditional 
			approach and a P3 procurement by 8.5 percent per year. As discussed 
			above, this adjustment is intended to reflect that money spent in 
			the near term is more valuable than money spent in the future. In 
			the past, our office has suggested that a 5 percent discount rate be 
			used for such analyses, but acknowledges there is no one "right" 
			discount rate. We also note that the state's long–term borrowing 
			rate is currently less than 5 percent. 
			Unjustified Tax Adjustment. 
			The VFM analysis for this project also included a $167 million 
			adjustment in order to account for increased tax revenues (such as 
			from corporate taxes) that the private developer would pay to the 
			state under the P3 approach. The analysis assumed that if the 
			project was not procured as a P3, the state would not receive these 
			additional revenues. However, we found the adjustment included 
			mostly revenues related to potential federal taxes, which would not 
			directly benefit the state. Thus, the adjustment made a P3 approach 
			look more favorable than is warranted. 
			Assumed Early Payment of Cost 
			Overruns. Under a more traditional procurement 
			approach (such as design–bid–build), Caltrans assumed the Presidio 
			Parkway project would exceed its budget by $125 million and that 
			such cost overruns would need to be paid for at the start of 
			construction. However, such overages do not typically occur at the 
			start of a project, but rather as a project progresses through 
			construction. While some consideration of the potential for cost 
			overages is reasonable, Caltrans' method relies on subjective 
			judgment rather than objective evidence. Consequently, the chosen 
			method has the effect of overstating the net present cost of the 
			project under a traditional procurement approach, thereby favoring a 
			P3 procurement approach for the project. 
			Failed to Account for Competitive 
			Bidding Environment. The Caltrans' VFM analysis, which 
			was prepared in February 2010, also did not take into account the 
			competitive construction bidding environment that occurred around 
			that time. During this period, Caltrans awarded construction 
			contracts that were on average 30 percent below the project's 
			original cost estimate. While it is not possible to know exactly 
			what the bids would have been if the Presidio Parkway project had 
			been procured using a more traditional procurement, it appears 
			reasonable to assume that the project could have been awarded at a 
			much lower cost than the engineer's cost estimate. 
			Our analysis indicates that utilizing a different set of 
			assumptions (such as a discount rate of 5 percent and excluding the 
			assumed tax adjustment) would result in the cost of the Presidio 
			Parkway project being less—by as much as $140 million in net 
			present value terms—in the long run under a traditional procurement 
			approach than the chosen P3 approach. 
			Assumptions in Long Beach Courthouse Analysis Favored 
			P3. Some of the key assumptions in the VFM analysis of 
			the Long Beach courthouse that tended to favor P3 procurement 
			include: 
			
				- Unjustified Tax Adjustment. 
				Similar to the Presidio Parkway project, the VFM analysis for the 
				Long Beach courthouse project included a $232 million adjustment to 
				account for increased tax revenues that would be paid for by the 
				private developer under the P3 approach. A major component of this 
				adjustment reflects revenues from federal taxes. Since additional 
				federal tax revenues would not directly benefit the state, there 
				appears to be little to no justification for increasing the cost of 
				using a traditional procurement approach to reflect the federal 
				taxes that would be paid by a private developer. 
- Overstated Cost Overruns. 
				The VFM analysis assumed that using AOC's more traditional 
				procurement approach of construction manager at risk—rather than a 
				P3 procurement approach—would result in construction cost overruns 
				for the Long Beach courthouse project totaling $128 million (about 
				30 percent of the project's estimated cost). However, given that AOC 
				has procedures in place to prevent such cost overages and has not 
				experienced them with recent court construction projects, this 
				assumption has the effect of overstating the cost of the project 
				under a construction management at risk approach. 
- Leasing of Additional Space. 
				The AOC's VFM analysis assumes that under the P3 approach, the 
				courthouse project would include space that would initially be 
				leased by the private developers to other entities, but could 
				eventually be used by the court. The VFM analysis also assumes this 
				additional space would be needed by the court in Long Beach in the 
				future, and builds the cost of leasing this additional space into 
				its estimates. This factor adds $260 million in costs to a 
				traditional procurement of the Long Beach courthouse project, but 
				only $69 million to the cost of the P3. The higher cost under a 
				traditional approach assumes that a separate building would be 
				leased and that the leased building would need substantial 
				modifications. The analysis for the traditional procurement also 
				assumes increased costs for security officers to monitor the leased 
				building. While there is some basis for estimating a higher cost for 
				the potential need to lease additional space under a traditional 
				procurement approach, the AOC has not conclusively demonstrated that 
				all of this additional space would be needed by the court in Long 
				Beach. Moreover, AOC's other courthouse construction projects 
				ordinarily do not include this kind of extra space.
- Project Completion. 
				The AOC–s VFM analysis assumes that it would take 14 months longer 
				to complete the Long Beach courthouse under construction manager at 
				risk procurement than as a P3 project. Accordingly, the analysis 
				uses different timelines to discount the costs of the project under 
				each type of procurement. The way the VFM analysis adjusts for these 
				assumed differences in timing effectively increases the cost of a 
				traditional procurement in net present value terms. However, it is 
				not evident that such a procurement would necessarily take 14 months 
				longer—especially in view of the considerable flexibility state law 
				gives AOC with respect to its construction contracting methodology. 
Our analysis indicates that utilizing a different set of 
			assumptions than those discussed above (such as excluding the 
			assumed federal tax adjustment and leasing costs) would result in 
			the cost of the Long Beach courthouse project being less—by as much 
			as $160 million in net present value terms—in the long run under a 
			traditional procurement approach than the chosen P3 approach. 
			State Law Lacks Thorough Project Approval Processes
			Our analysis found that for both the Presidio Parkway and Long 
			Beach courthouse projects, the state did not utilize a thorough 
			process for selecting P3 projects. Having thorough processes in 
			place could have prevented Caltrans and AOC from entering into a P3 
			agreement for each project, or at least required changes to 
			negotiate lower prices and better ensure that the intended P3 
			benefits are achieved.
			For P3 transportation projects, state law requires the CTC to 
			conduct a limited review of the basic features of each project 
			sponsored by Caltrans or a regional transportation agency. (We note 
			that in reviewing the Presidio Parkway project, CTC extended its 
			evaluation beyond the basic requirements to further review the 
			project's financing.) However, state law does not require the 
			commission or another entity to conduct an overall review of whether 
			(1) the state would benefit from procuring a particular project as a 
			P3 and (2) whether a particular P3 contract is structured to 
			maximize the state's benefits. Moreover, while state law does 
			provide a 60–day period for the appropriate legislative fiscal and 
			policy committees and PIAC to review P3 proposals before Caltrans 
			can sign an agreement with a private developer, state law does not 
			require that Caltrans address any of the concerns raised in these 
			reviews. 
			For court construction projects, state law authorizes the Joint 
			Legislative Budget Committee and DOF to review a potential P3 
			project before AOC can fully develop the project's concept. 
			Accordingly, the Legislature reviewed and approved the general 
			criteria used by AOC to select the private partner for the Long 
			Beach courthouse project. However, the Legislature did not have an 
			opportunity to review and comment on the VFM analysis before it was 
			finalized and the contract was signed with the private developer. 
			State Lacks P3 Expertise
			As previously discussed, experts recommend that government 
			entities develop expertise regarding P3s in order to better protect 
			public resources when entering into large contracts with private 
			developers. Our review, however, finds that such expertise within 
			state government has not been sufficiently developed in California. 
			PIAC Has Limited P3 Expertise. The PIAC 
			was established in 2009 to assemble and share research on best 
			practices and lessons learned from transportation P3s around the 
			world. However, based on our discussions with staff at the BT&H 
			Agency and our review of various PIAC documents (including the 
			minutes from the seven PIAC meetings that have taken place), we find 
			that PIAC has done little to implement best practices for 
			transportation P3s. The only steps that PIAC appears to have taken 
			in this regard are to post reports containing information on P3 best 
			practices on its website and to contract for two reports on P3s. We 
			also note that the commission currently lacks members with in–depth 
			expertise on issues such as state financing, state procurement, and 
			state labor issues. Perspectives on these issues could help to 
			ensure that the state maximizes its benefits when using P3s.
			No Systematic Approach for Reviewing Lessons Learned. 
			Our review also finds that the state does not have a systematic 
			process for identifying and applying lessons learned from prior P3 
			projects. Although Caltrans is the only state agency to have entered 
			into multiple P3 agreements, it currently lacks a formal process for 
			reviewing past P3 projects in order to maximize benefits and avoid 
			repeating past mistakes. We understand that AOC is currently 
			developing a review and reporting process for the Long Beach 
			courthouse project. Once completed, these reports may provide 
			helpful lessons learned about AOC's use of P3 procurement. 
			Recommendations to Maximize State Benefits from P3s
			 In this report, we reviewed the state's experience with P3s and 
			identified several instances where the best practices identified in 
			existing P3 research have not necessarily been followed. Based on 
			our review and findings, we have identified several opportunities 
			for the state to further maximize its benefits when deciding to 
			procure a state infrastructure project as a P3. Our specific 
			recommendations are summarized in Figure 8 and discussed in detail 
			below. 
							
			
			Specify P3 Project Selection Criteria
			As previously mentioned, the state's processes for selecting P3 
			projects are inadequate and not necessarily based on selection 
			criteria identified in the research as best practices. Accordingly, 
			we recommend that the Legislature adopt legislation requiring that 
			each state department with P3 authority utilize certain criteria 
			when evaluating whether a particular project should be procured as a 
			P3. According to the research, these selection criteria should not 
			be highly prescriptive, but rather should provide general guidance 
			regarding the selection of potential P3 projects. Such an approach 
			would provide for greater consistency across departments in terms of 
			how P3 projects are selected. The selection criteria should include 
			being a technically complex project, as well as a project that can 
			transfer risks to a private partner and benefit from non–state 
			financing. In addition, the Legislature may want to specify whether 
			P3 projects must have a revenue source, such as a user fee. 
			Require Analysis of a Range of Procurement Options
			In order to determine which procurement approach would most 
			effectively benefit the state, we recommend that the Legislature 
			adopt legislation requiring a comparative VFM analysis of a range of 
			procurement options (including design–bid–build, design–build, and 
			P3) for all potential P3 infrastructure projects. Evaluating a range 
			of procurement options would allow the state to better balance the 
			potential benefits of increased private sector involvement with the 
			potential risks unique to each project. In contrast, the benefit of 
			evaluating only two procurement approaches—as was done by Caltrans 
			and AOC—can be limited. This is because it does not evaluate other 
			options (such as design–build), which in some cases may be the best 
			option. 
			We also recommend that the Legislature specify in statute that 
			such VFM analyses: 
			
				- Exclude Federal Tax Adjustments. 
				Increased federal tax revenues do not directly benefit the state and 
				should not be included in a VFM analysis.
- Apply Costs to Expected Year of 
				Expenditure. Project costs should be accounted for in 
				the year they are likely to be incurred, in order to effectively 
				estimate the project's likely total cost in the long run.
- Use Current Construction Cost 
				Estimates. Construction cost estimates should be based 
				on the current bidding environment in the state. 
- Include a Sensitivity Analysis. 
				A sensitivity analysis can help to indicate how the results of the 
				VFM analysis might change with a different set of assumptions. 
				Specifically, this analysis should evaluate project costs and 
				revenues with a range of reasonable discount rates to show how 
				differing assumptions can influence the outcome of the VFM analysis. 
				If a project will generate revenue, such as from tolls or fares, a 
				reasonable range of revenues should also be evaluated in the 
				sensitivity analysis.
Modify Structure and Responsibilities of PIAC
			In order to help ensure that PIAC effectively assembles and 
			shares research, best practices, and lessons learned from 
			transportation P3s around the world, we recommend the Legislature 
			adopt legislation to:
			
				- Expand PIAC's Authority. 
				In order to provide a consistent review and approval process for the 
				use of P3 procurement, we recommend 
				expanding the PIAC's role to require the commission to approve all 
				state P3 projects, as discussed in detail later in this report. We 
				also recommend expanding the scope of PIAC to all types of 
				infrastructure projects, rather than only those related to 
				transportation. Having the commission involved in all types of P3 
				will further the state's P3 expertise. To reflect this broader 
				scope, we also recommend making PIAC an independent commission, 
				rather than part of the BT&H Agency.
- Direct PIAC to Evaluate Other 
				Departments for P3 Authority. We have found that 
				certain types of projects may benefit the state if procured using a 
				P3. It is possible that state departments other than Caltrans, AOC, 
				and HSRA will have projects meeting these P3 criteria. Accordingly, 
				we recommend that the Legislature direct PIAC to review the types of 
				projects planned by other state departments and recommend to the 
				Legislature whether P3 authority should be granted to additional 
				state departments. 
- Broaden PIAC's Expertise. 
				In order to ensure that PIAC has the expertise necessary to advise 
				state departments on all types of P3s, we believe it would be 
				beneficial for the commissioners to have a broad mix of expertise 
				related to P3, as well as state finance and procurements. 
				Specifically, we recommend that the Legislature appoint some of the 
				commissioners and that, in addition to P3 experts, the 
				commission include the Director of the Department of General 
				Services (or a representative), and the State Treasurer (or a 
				representative). The Legislature could also consider reducing the 
				number of commissioners on PIAC to a more manageable size.
- Require PIAC to Develop and 
				Implement Best Practices. We recommend requiring PIAC 
				to (1) develop a set of best practices for P3 projects in 
				California, (2) provide state departments specific steps for 
				implementing those best practices, and (3) provide technical 
				assistance to state agencies planning to pursue a P3. Consistent 
				with the research, it would benefit the state to have such expert 
				advice provided from the initial project screening stage through the 
				procurement and administration of a P3 contract. We also recommend 
				that the Legislature require periodic reports from PIAC in its 
				efforts in developing and implementing P3 best practices. 
Improve Consistency of state's P3 Approval Process
			We recommend that the Legislature adopt legislation to make the 
			process for reviewing and approving P3 projects consistent and 
			thorough across those state departments authorized to pursue such 
			projects. Specifically, we recommend requiring the use of the review 
			and approval process summarized in Figure 9 and discussed in detail 
			below.
			
				 
			 		
			
			Require PIAC to Approve P3 Concept and VFM Analysis. 
			Our above recommendations to modify the structure and 
			responsibilities of PIAC would make it well–suited to review and 
			approve a department's proposed use of P3 procurement. As shown in 
			Figure 9, we recommend that the Legislature require departments to 
			provide a VFM analysis and other relevant project information (such 
			as draft procurement documents) on all proposed P3 projects to PIAC. 
			Under our recommended process, if PIAC identifies 
			concerns with a P3 proposal, the commission would require the 
			department sponsoring the project to perform additional analyses and 
			resubmit the proposal for subsequent review. If a project does not 
			satisfy the above P3 criteria, we recommend that PIAC have the 
			authority to reject the use of a P3 approach, and direct the 
			department to use another procurement method. Thus, we recommend 
			that the Legislature adopt legislation directing PIAC to implement a 
			process to evaluate (1) whether a P3 project proposal is consistent 
			with the scope and cost approved in the state's current capital 
			outlay processes (meaning either by the Legislature or CTC) and (2) 
			whether using a P3 approach would be the best procurement option.
			Conclusion
			Based on our review of existing research, we believe that P3 
			procurement—if done correctly—has merit and may be the best 
			procurement option for some of the state's infrastructure projects. 
			In certain instances, sharing risks with a private partner and using 
			a diverse financing package (including private loans) may even be 
			the only way to build those projects that are both very complex and 
			expensive. For such projects, the use of P3 procurement can make the 
			price and schedule more certain by transferring various project 
			risks to a private partner. In addition, access to specialized 
			expertise and private financing could have the effect of 
			accelerating projects and providing other benefits to the state. 
			However, the state does give up considerable control over the 
			management and long–term funding priorities of a project that is 
			constructed under a P3 approach. This limitation and others must be 
			considered carefully when considering a decades–long partnership.
			We also find that implementing certain P3 best practices 
			identified in the research can better ensure that the intended 
			benefits of P3s to the state are achieved. Thus, in order to 
			maximize the state's benefits from P3s, we recommend that the 
			Legislature take a series of steps to ensure that such best 
			practices are followed in developing and implementing future P3 
			projects. For example, we recommend specifying P3 project selection 
			criteria and improving the state's approval process to utilize an 
			entity with expertise in P3s. More importantly, our proposals to 
			develop P3 expertise and better evaluate potential P3 projects would 
			provide for a better understanding of the actual benefits and 
			limitations of P3 projects. Finally, as the state gains experience 
			with P3s, the Legislature may want to consider whether the existing 
			P3 authorization provided to Caltrans and AOC should be expanded to 
			other departments.