Department of Motor Vehicles
|
The budget requests $25 million for working drawings and construction of the (1) Fresno field office replacement and (2) Redding and Oakland field office reconfiguration projects.
|
Reduce by $23.7 million. Our review of project timelines shows that the DMV will not be able to begin construction for these three projects in the budget year. Recommend that the Legislature approve funding only for the working drawings phase of these projects—Fresno ($1,174,000), Oakland ($155,000) and Redding ($237,000). Construction funding can be provided in the 2011-12 budget without causing project delay.
|
2-02-10
|